How to Calculate Concrete for a Slab (With Examples)

Learn how to calculate concrete for a slab: the cubic yard formula, a worked example, waste factor, bags of premix needed and the metric version, step by step.

To calculate concrete for a slab, multiply length × width × thickness, with all three in feet, to get cubic feet, then divide by 27 to get cubic yards. Add 5 to 10 percent for waste. For example, a 10 × 12 foot slab that is 4 inches thick needs 40 cubic feet, or about 1.48 cubic yards, before waste.

That is the core formula. Below is a step-by-step method, a fully worked example, how to convert to bags of premix, a metric version and the mistakes that leave people short on pour day.

Quick steps: how to calculate concrete for a slab

  1. Measure the length and width of the slab in feet.
  2. Convert the thickness to feet by dividing inches by 12. Four inches is 0.333 ft.
  3. Multiply length × width × thickness to get cubic feet.
  4. Divide by 27 to convert cubic feet to cubic yards.
  5. Add a waste factor of 5 to 10 percent.
  6. Convert to bags if you are not ordering ready-mix: divide cubic feet by the yield per bag.
  7. Round up, never down.

The concrete slab formula explained

The formula is just the volume of a box:

Cubic yards = (Length ft × Width ft × Thickness ft) ÷ 27

Why 27? A cubic yard is 3 ft × 3 ft × 3 ft, which equals 27 cubic feet. Ready-mix concrete in the US is sold by the cubic yard, so that is the number your supplier needs.

The one place people trip up is thickness. Slab thickness is almost always given in inches, but length and width are in feet. Mixing units without converting gives an answer that is 12 times too big. Divide inches by 12 first:

Thickness In feet
3 in 0.25 ft
4 in 0.333 ft
5 in 0.417 ft
6 in 0.5 ft
8 in 0.667 ft

If a measurement includes inches, like 12 ft 6 in, convert that too: 6 ÷ 12 = 0.5, so it is 12.5 ft.

Worked example: a 10 × 12 ft patio slab, 4 inches thick

Let’s run the numbers on a common backyard patio.

Step 1: Convert thickness. 4 in ÷ 12 = 0.333 ft.

Step 2: Find cubic feet. 10 × 12 × 0.333 = 40 cubic feet.

Step 3: Convert to cubic yards. 40 ÷ 27 = 1.48 cubic yards.

Step 4: Add waste.

  • With 5 percent: 1.48 × 1.05 = 1.56 cubic yards
  • With 10 percent: 1.48 × 1.10 = 1.63 cubic yards

For a ready-mix order, you would likely round up to 1.75 cubic yards, depending on the increments your supplier sells in.

Quick coverage rule of thumb

Flip the math around and one cubic yard covers about:

  • 81 sq ft at 4 inches thick
  • 65 sq ft at 5 inches thick
  • 54 sq ft at 6 inches thick

So a 400 sq ft driveway at 5 inches needs roughly 400 ÷ 65 = 6.2 cubic yards before waste. It is a handy sanity check when you are standing at the supplier’s counter.

How much waste to add, and why

Even a careful pour uses more concrete than the perfect math says. The extra goes to:

  • Uneven subgrade. A dip of half an inch across a large slab adds up fast.
  • Forms that bow slightly outward under the weight of wet concrete.
  • Spillage from the wheelbarrow, chute or mixer.
  • Concrete left in the mixer or stuck to tools.

Use 5 percent for small, well-prepared slabs with a level, compacted base and sturdy forms. Use 10 percent for larger slabs, uneven ground, or if this is your first pour. Running short mid-pour is far worse than having a little left over, because the first section can start to set before more concrete arrives, leaving a weak joint.

How many bags of concrete for a slab

For small slabs, you may mix bagged premix yourself. Yield depends on the bag size. Typical figures are:

  • 80 lb bag: about 0.6 cubic feet
  • 60 lb bag: about 0.45 cubic feet

Always check the bag, because yields vary a little by brand and mix.

Formula: Bags = cubic feet ÷ yield per bag

Using the 10 × 12 ft, 4 in slab (40 cubic feet):

Bag size No waste With 10% waste (44 cu ft)
80 lb (0.6 cu ft) 40 ÷ 0.6 = 66.7, so 67 bags 44 ÷ 0.6 = 73.3, so 74 bags
60 lb (0.45 cu ft) 40 ÷ 0.45 = 88.9, so 89 bags 44 ÷ 0.45 = 97.8, so 98 bags

That is a lot of bags. At 80 lb each, 74 bags weigh nearly 6,000 lb. Mixing that by hand before the first batch starts to stiffen is a big job, which is why many people order ready-mix for slabs this size. For a cubic yard, you would need about 45 bags at 80 lb or 60 bags at 60 lb.

Metric version: concrete for a slab in cubic meters

If you work in metric, the math is even simpler because there is no divide-by-27 step.

Cubic meters = Length m × Width m × Thickness m

Convert thickness from millimeters to meters by dividing by 1,000. For example, 100 mm = 0.1 m.

Worked example: a 3 × 4 m slab, 100 mm thick

  • Volume: 3 × 4 × 0.1 = 1.2 cubic meters
  • With 5 percent waste: 1.2 × 1.05 = 1.26 cubic meters
  • With 10 percent waste: 1.2 × 1.10 = 1.32 cubic meters

Bagged concrete in metric countries often comes in 20 or 25 kg bags. Check the yield printed on the bag, then divide your volume by it. Remember that 1 cubic meter equals 1,000 liters, so if a bag says it yields about 12 liters, that is 0.012 cubic meters per bag, and 1.32 ÷ 0.012 = 110 bags.

Calculating other slab shapes

Not every slab is a neat rectangle.

L-shaped slabs

Split the L into two rectangles, calculate each one separately, and add the volumes together. Do not overlap the corner square, or you will count it twice.

Circular slabs

Use the area of a circle: π × radius² × thickness. For an 8 ft diameter round pad at 4 inches, the radius is 4 ft: 3.1416 × 16 × 0.333 = 16.8 cubic feet, or about 0.62 cubic yards.

Slabs with thickened edges

Many slabs have a deeper edge or footing around the perimeter. Calculate the flat slab, then calculate the thickened edge as a long, narrow box: perimeter length × extra width × extra depth. Add the two together.

Common mistakes that leave you short

  • Forgetting to convert inches. Always divide inches by 12 before multiplying.
  • Measuring the wrong thickness. Measure the depth of your forms at several points, not just one corner. If the base is uneven, average it.
  • Rounding down. Always round bags and yards up.
  • Skipping the waste factor. The formula gives the theoretical minimum.
  • Ignoring footings, steps or post holes that are part of the same pour.

The easy way: BuildCalc on your phone

If you would rather not juggle conversions on a dusty job site, a construction calculator handles it as you type. BuildCalc: Construction Calc by Genzz includes concrete calculators for rectangular, L-shaped and circular slabs, plus footings, columns, steps, bags to yards, rebar and mix ratios.

A few things that help with slab math:

  • Enter feet, inches and fractions the way you read your tape, like 12’ 6 1/2”, on a big, glove-friendly keypad.
  • Switch between imperial and metric with one tap, and every input and result converts.
  • Set your country once for the right units and bag sizes, such as 80 lb or 25 kg bags.
  • See the formula and source behind every result, so you can double-check the math yourself.
  • Job packs let you enter a slab size once and get concrete, rebar and gravel together.

It works fully offline, so it still works in a basement with no signal. And if your phone takes a splash from the hose during cleanup, here is how to get water out of a phone speaker.

Like any calculator, it gives estimates to help you plan. Follow your local building code, the manufacturer’s instructions and a licensed professional for structural work. If a contractor sends you a quote to approve, you can sign the PDF on your Android phone without printing it.

Bottom line

To calculate concrete for a slab, multiply length × width × thickness in feet, divide by 27 for cubic yards, and add 5 to 10 percent for waste. A 10 × 12 ft slab at 4 inches needs about 1.48 cubic yards before waste, or roughly 74 bags of 80 lb premix with 10 percent extra. In metric, just multiply meters together. Measure carefully, always round up, and let a calculator handle the conversions when you are on site.

Frequently asked questions

How many cubic yards of concrete do I need for a 10 x 10 slab?

At 4 inches thick, a 10 by 10 foot slab needs 10 x 10 x 0.333 = 33.3 cubic feet, which is about 1.23 cubic yards. Add 5 to 10 percent for waste and plan on about 1.3 to 1.36 cubic yards.

How many 80 lb bags of concrete make a cubic yard?

An 80 lb bag of premix yields about 0.6 cubic feet. A cubic yard is 27 cubic feet, so you need 27 divided by 0.6, which is 45 bags per cubic yard. With 60 lb bags at about 0.45 cubic feet each, you need 60 bags.

How thick should a concrete slab be?

Four inches is common for patios, walkways and shed floors. Driveways and slabs that carry heavier loads are often 5 to 6 inches. Always check your local building code and any engineering plans for your project.

Should I use bags or order ready-mix concrete?

Bags make sense for small jobs like post footings, steps or a small pad. For larger slabs, mixing dozens of bags by hand is hard to finish before the concrete starts to set, so many people order ready-mix. Compare prices and delivery minimums with local suppliers.